Name: PUBLIC UTILITY DISTRICT NO. 1
Application Date: 3/27/2017
Site Address: 83 Idea Pl
Issue Date: 12/1/2017
Status: Finaled
System In Use Date: 2/20/2018
Sewer Permit: SWR2017-00029
Description: Zenovic's IAD letter received 4-9-18##2-20-18 per RB: OK to cover gravity connection at
south end of parcel. Zenovic & Associates will oversee the remaining installation and provide an IAD
letter.
Parcel(s) related to this case:
(Principle Parcel: Active)
(Related Parcel: Active)
(Related Parcel: Active)
(Related Parcel: Active)
(Click the Parcel Number for more information)
Documents related to this case:
Case Process Steps (Review, Decisions, Inspections, etc.)
Plan Review (H)
DONE
Received: 10/23/2017... ... Completed: 10/27/2017
Septic Decom Permit Required
H
DONE
Required: 12/1/2017... ... Approved: 12/1/2017
Issue Side Sewer Permit
DONE
... ... Issued: 12/1/2017
OK to Cover / In Use
DONE
... ... Connection In Use: 2/20/2018
Side Sewer Inspection
DONE
Required: 11/16/2017... ... Done: 2/20/2018
OK to cover gravity connection at south end of parcel. Zenovic & Associates will oversee the remaining
installation and provide and IAD letter.
Final Side Sewer Permit
DONE
... ... Finaled: 4/16/2018
-Septic Decom Final Reqd
DONE
Requirement Placed: 11/16/2017... ... Requirement Met: 4/16/2018
No decommissioning required; see As Builts per J. Smith on 4-16-18