Application Date: 11/27/2018 |
Site Address: 970 Carlsborg Rd |
Status: Finaled
System In Use Date: 12/27/2018 |
Sewer Permit: SWR2018-00015
Description: Existing maintenance building & wash rack |
Connection fees for this permit assessed at 3 ERUs, total 5 ERUs for whole site that includes |
SWR2018-00004 & SWR2018-00009. ERU reassessment conditions see attached letter dated |
12/20/18. |
Parcel(s) related to this case: |
(Principle Parcel: Active)
(Click the Parcel Number for more information) |
Documents related to this case: |
Case Process Steps (Review, Decisions, Inspections, etc.) |
Plan Review (H)
DONE
Received: 11/26/2018... ... Completed: 12/20/2018 |
Request Add'l Application Info
DONE
... Request Sent: 12/20/2018... Rec'd/Cancelled: 12/20/2018 |
Issue Side Sewer Permit
DONE
... ... Issued: 12/20/2018 |
Side Sewer Inspection
DONE
Required: 12/20/2018... ... Done: 2/1/2019 |
OK to Cover / In Use
DONE
... ... Connection In Use: 2/1/2019 |
-Septic Decom Final Reqd
AUTO
Requirement Placed: 12/20/2018... ... Requirement Met: 7/10/2019 |
Final Side Sewer Permit
DONE
... ... Finaled: 7/12/2019 |