Name: P.U.D. #1 OF CLALLAM COUNTY
Application Date: 9/22/1997
Site Address: Idea Pl
Issue Date: 12/2/1997
Status: Finaled
Finaled Date: 7/6/1998
Building Permit: BPT97-00965
Subtype: Commercial
Description: P.U.D. OPERATIONS CENTER - OFFICE/TRUCK BAYS/WAREHOUSE w/ FIRE ALARM
"99.9" = Engineer's "Installed as Designed" letter required prior to final. R.B. 9-2-97 / PLAT
ALTERATION MUST BE FINALED PRIOR TO FINAL BLDG. INSP.
Parcel(s) related to this case:
(Principle Parcel: Active)
(Click the Parcel Number for more information)
Documents related to this case:
Case Process Steps (Review, Decisions, Inspections, etc.)
Septic/Water/Drainage/Rd Appr
Done
... ... Date: 12/2/1997
Issue permit (F)
Done
... ... Date Approved: 12/2/1997
Renew Building Permit
Done
... ... Renewed: 7/9/1998
Miscellaneous inspection
Done
... ... Done: 2/25/1998
shearnailing roof not approved
Insulation inspection
Done
... ... Required: 3/19/1998
Final sign-off
Done
... ... Finaled: 7/6/1998
Miscellaneous inspection
Done
... ... Done: 7/28/1998
final not approved
Final sign-off
Done
... ... Finaled: 9/3/1998
Foundation/Setbacks Insp.
Open
... Scheduled: 12/10/1997...
footing approved
Foundation/Setbacks Insp.
Open
... Scheduled: 12/16/1997...
walls approved
Foundation/Setbacks Insp.
Open
... Scheduled: 12/18/1997...
footing approved
Plumbing Inspection
Open
... Scheduled: 12/22/1997...
rough under gr. approved
Foundation/Setbacks Insp.
Open
... Scheduled: 12/29/1997...
walls approved
Foundation/Setbacks Insp.
Open
... Scheduled: 1/8/1998...
footing, walls & t beam approved
Foundation/Setbacks Insp.
Open
... Scheduled: 2/12/1998...
pad footing approved
Foundation/Setbacks Insp.
Open
... Scheduled: 2/23/1998...
footing approved
Plumbing Inspection
Open
... Scheduled: 3/12/1998...
rough in not approved
Framing inspection
Open
... Scheduled: 3/12/1998...
not approved
Plumbing Inspection
Open
... Scheduled: 3/13/1998...
rough in approved
Framing inspection
Open
... Scheduled: 3/13/1998...
not approved
Framing inspection
Open
... Scheduled: 6/8/1998...
steel stud not approved
Plumbing Inspection
Open
... Scheduled: 7/6/1998...
final approved
Plumbing Inspection
Open
... Scheduled: 7/8/1998...
not approved/nobody on site
Plumbing Inspection
Open
... Scheduled: 10/5/1998...
HYDRANT FLUSH APPROVED